Construction Phase

Project Summary

The project includes new construction of approximately 260,000 gross square feet on the existing Shaun F. Beasley Track and Field. The project site is approximately 19.3 acres, comprising the new Shaun F. Beasley Track and Field and the existing high school building and parking acreage. The configuration of the new construction will feature preferred programmatic adjacencies with three-story L-shaped academic pods, optimized for best fit to avoid phased construction.

(Construction Phasing: “Buildings A-F”)

Construction Working Hours

Monday through Friday: 6 a.m. to 7 p.m.

Saturdays, when necessary: 6 a.m. to 7 p.m.

Construction Progress Photos

(click on the photos to enlarge with descriptions)

Week of September 04, 2026

Building "C" - Installation of wood slat ceiling in Student Common.
Concrete poured for front entrance sidewalk.
Building "D" - Installation of maple gym flooring.
Installation of Fire Extinguisher Cabinents.

Week of August 28, 2026

Building "A" - Installation of pavers on Greenhouse roof terrace.
Building "E" - Installation of theater stage battens.
Building "C" - Installation of kitchen appliances.
Building "D" - Installation of new Gym floor.

Week of August 21, 2026

Plantings along Wiley Street abutters.
Building "E" - Delivery/loading of Solar Panels.
Building "C" - Terrazzoo flooring progress in Student Common area.
Building "D" - Installation of gym subfloor.

Week of August 14, 2026

Current Progress of future "Outdoor Learning Commons."
Building "C" - Installation of metal panels at the main entrance canopy is complete.
Building "C" - Installation of lockers and lighting fixtures in locker rooms.

Week of August 07, 2026

Building "E" -  Installation of the Auditorium acoustic “sound cloud” is complete.
Building "C" - Installation of Learning Stair railing.
Installing the wooden guardrail along emergency vehicle access road around the east side of building.

Week of July 31, 2026

Excavation for underground utilities in preparation ahead of the future Hemlock RD realignment (Scheduled Summer 2027).
Building "B" - Assembling rolling tables in science lab classrooms.
Building "E" - Acoustic “sound clouds” installed in band room.

Week of July 24, 2026

Building "C" - Installation of Media Center Reception/Circulation Desk.
Building "D" - Installation of hollow metal doors on 1st floor.
Building "F" - Concrete Slab placement at Loading Dock.

Week of July 17, 2026

Building "D" - Installation of auditorium "cloud" ceiling is in progress.
Future Outdoor Student Commons - current progress.
Building "C" - Installation of terrazzo flooring in Kitchen servery area.
Building "C" - Main Entrance current progress.

Week of July 10, 2026

Building "D" - Installation of  gymnasium acoustical subflooring system.
Building "C" - Installation of terrazzo (bridge) is nearing completion.
Building "C" - Installation of specialty ceiling over Learning Stairs.

Week of July 03, 2026

Building "B" - Installation of doorway millwork "portals" is ongoing.
Outdoor Amphitheatre progress.
 Installation of pavers outside Building "A/B"

Week of June 26, 2026

Building "D" - Installation of Bathroom wall tile.
 Installation of Terrazzo flooring in Cafeteria/Student Common.
Building "D" - Installation of rubber athletic flooring in Fitness Studio.

Week of June 19, 2026

Building "C" - Poured Terrazzo Flooring commenced on second floor above the Student Common.
 Installation of granite and precast blocks at new outdoor amphitheater.
Building "F" - Installation of climbing wall/surface in new gymnasium.

Week of June 12, 2026

Building "C" - Installation of Terrazzo Flooring commenced on second floor above the Student Common.
Building "C" - Installation of interior Glass in ongoing.
Building "F" - Installation of Linoleum flooring in the new School Department Central Office.

Week of June 05, 2026

Building "A" - Installation of Linoleum flooring in the academic wing corridors.
Building "C" - Subshades in Media Center.
Building "C" - Men's locker room progress.

WMGLD Energy Park Update

(click on the photos to enlarge with descriptions)

“almost all equipment is there (on-site), and we are commissioning the generator and switchgear right now, while also testing the “blackstart” setup on the battery. The battery has been running as a peak shaver since June 2025, and the generator should be doing the same thing by the end of the year.

Over the winter, we (WMGLD) will be programming the microgrid controller to control the battery and generator automatically in the event of an outage. 

We (WMGLD)  are also working on energizing both schools’ transformers before the winter – this should be complete by  early December.”*

*December 2025 Update provided Vincent McMahon (Senior System’s Engineer, Wakefield Municipal Gas & Light Department)

WMGLD (Wakefield Municipal Gas & Light Department) Energy Park Project progress - October 2025.
Energy Park Project - Battery Storage Units - Powered by excess PV (Solar Panels on WMHS/NEMT rooftops) power generation to be utilized as "back-up" power for both Schools.